Before
filling out the forms supplier/ owner/ consumer are advised
to ensure that all fields are filled properly in forms and enclose/submit all
relevant documents. The supplier/ owner/ consumers are also advised to carefully
review the “Schedule” in “Central Electricity Authority (Measures
relating to Safety and Electric Supply) Regulations, 2023” to identify the
necessary documents and attach them accordingly before proceeding with the form
submission. Ensuring that all required documents/ Annexure are properly
prepared/ filled and attached will facilitate a smoother application process
and prevent any delays or rejections.
Desired documents/
detail specifically required to be filled or supplied is detailed below:
1) List
of equipment mention the data: (Name, Make, Sr. No., MW/KW, KVA, Quantity).
2) Single
line diagram with metering & protection.
3) Drawing
showing the location, layout, elevation and section.
4) Drawing
of earthing with Electrodes/Mats.
5) Manufacturer’s
test certificate for each equipment.
6) Insulation
test results and earth resistance of individual, combined electrodes and
earthmat.
7) Details
of electrical Contractor and Supervisor (enclose copy).
8) Copy
of treasury Challan receipt.
9) Copy of NOC from supplier in case of D.G. set to be commissioned as standby source of supply.
FORM-I : FORM FOR APPROVAL TO ENERGISE ELECTRICAL INSTALLATIONS OF VOLTAGE UP TO AND INCLUDING 250 V.
FORM-II : FORM FOR APPROVAL TO ENERGISE ELECTRICAL INSTALLATIONS OF VOLTAGE LEVEL MORE THAN 250 V AND INCLUDING 650 V.
FORM-III : FORM FOR APPROVAL TO ENERGISE ELECTRICAL INSTALLATIONS OF VOLTAGE EXCEEDING 650 V.
FORM-IV : FORM FOR APPROVAL TO ENERGISE ELECTRICAL INSTALLATIONS IN MINES.
Chief Electrical Inspector,
Himachal
Pradesh, Shimla-09